SITEBRAID RESOURCE / PUCT PROJECT 58481

PUCT Project 58481: Texas Large-Load Owner Readiness Pack under adopted 16 TAC 25.194

A free owner-side guide to financial security, CIAC, customer-built interconnection facilities, TSP takeover and audit-ready documentation under adopted 16 TAC 25.194, effective October 8, 2026.

Large-load owners can face security postings, CIAC payments and advance equipment commitments before tenant revenue begins. A customer-built switchyard adds land, acceptance, ownership-transfer and retained-liability decisions.

This pack turns those overlapping obligations into an owner workflow and evidence checklist. It covers a typical utility-delivered CIAC project and an agreed customer-built route.

The commission adopted 16 TAC 25.194 on September 18, 2026, effective October 8, 2026. The non-refundable interconnection fee in the March proposal was removed. Financial security is now the greater of $50,000 per MW of contracted peak demand or study-allocated system upgrade costs, cash collateral is creditable between stages, and return is staged from energization. The Standard Large Load Interconnection Agreement form is deferred to a separate rulemaking and is not settled.

Handbook PDF

Complete operating toolkit: handbook PDF, formula-driven XLSX, editable Word forms, operational CSV registers, worked example, quick start, data dictionary, authority map, update log and license.

Download the handbook PDF

Download the complete toolkit

Version 3.2.0 · Verified locally 2026-09-18. Source-specific verification limits are in the authority map.

The examples are illustrative. Read the quick start and license in the ZIP before using a project copy.

What is inside

Handbook and worked example

Substantive guidance with a labeled 240 MW campus example, authority limits and release gates.

Editable control model

Cost-by-cost reconciliation, cash-to-finish, risk, contingency, retainage, earned-value future draws, a dedicated adopted-rule security calculator, all applicable checklist controls and critical-path scheduling.

Operating records

Editable release and exception forms, dated calculated CSV snapshots, input templates and a field dictionary.

Version and source record

Version 3.2.0. Actual verification review: September 18, 2026. Built against the adoption order in Project No. 58481 and the Texas Register acknowledgement recording the effective date.

Who should use it

Use it with owner development, finance, legal, engineering, procurement and project-controls teams before posting security, paying CIAC or releasing long-lead equipment.

Replace every generic control with the project's final rule, tariff, TSP requirements and executed agreements.

Primary sources and scope

  1. Order Adopting New 16 TAC 25.194, Project No. 58481, Item 218

    The adopted rule and commission responses.

  2. Texas Register acknowledgement, TRD 202604027, Item 219

    Records adoption with changes and the October 8, 2026 effective date.

  3. Texas Senate Bill 6, enacted text

    Statutory large-load framework.

  4. ERCOT Large Load Integration

    Current ERCOT large-load guidance and forms.

  5. PUCT Project 58481 docket

    Current filings and procedural status.

This resource distinguishes governing requirements, project-specific determinations and recommended owner controls. It is not legal, tax, accounting, engineering or regulatory advice.

Cite this resource

Title
PUCT Project 58481: Texas Large-Load Owner Readiness Pack under adopted 16 TAC 25.194
Publisher
Sitebraid
Canonical URL
https://sitebraid.dev/resources/puct-project-58481-filing-206-large-load-owner-readiness-pack/
Version
3.2.0
Reviewed

Author, methodology and update record

Author and publisher: Sitebraid. This owner-side synthesis separates source requirements, project-specific decisions and recommended controls. Use the primary sources below and the toolkit authority map to check applicability and source-specific review limits.

The version and review date above describe the resource record, not a new regulatory review. The toolkit includes the authority map, version update log and license. Citation, reuse and contact tools were added on ; that presentation update does not change the artifact version.

Apply this resource to your project

All core artifacts and editable toolkits are available without registration.

Request a capital-exposure review

Ask about resource updates through our contact page