The lease can promise tenant choice, transparent bills and independent service that the shared campus network cannot lawfully or operationally provide.
ILLUSTRATIVE FAILURE SCENARIO
How the problem unfolds
Assume the landlord proposes a master-metered campus with shared generation and internal cost allocation. One tenant requires direct utility contracting, another expects to choose its energy supplier, and a third wants a separately auditable renewable supply arrangement. The serving utility's territory and rules do not automatically support those promises. Meanwhile, the landlord remains responsible for minimum payments even if a tenant disputes its allocation. A technically attractive network has become an incompatible customer and credit model.
Hypothetical development case. Assumptions are not project results, quoted prices or predicted failure rates.
TEXAS / LAW, REGULATION & LOCAL REQUIREMENTS
The Texas constraints to resolve
Reviewed September 10, 2026
Development issues to resolve, not a legal opinion. Applicability depends on the parcel, provider, project configuration and current instruments. Texas counsel, the responsible authority and qualified technical specialists should confirm the route before commitments are made.
Which requirements apply to this campus?
Identify the electric territory, cooperative choice status where relevant, and proposed customer of record before promising tenant procurement rights.
For supply involving existing generation, identify registration history and the exact proposed transaction before applying the co-location provisions below.
Use these questions to direct the review, not to determine legal eligibility. Open the applicable constraint below for the source, consequence and next action.
Cooperative territory can change the tenant's procurement rightsTexas Utilities Code Chapter 41; actual cooperative status must be checked.
Texas basis. Section 41.051 places the customer-choice decision with the cooperative board. The chapter distinguishes the service and metering framework where choice is offered. Texas Utilities Code §§41.051–41.053
Campus consequence. A tenant expecting the retail options available at another Texas site may be asking for rights the campus cannot deliver. A private meter or shared network does not establish those rights.
Resolve before commitment. Confirm territory, choice status and the proposed customer-of-record structure with the provider and utility counsel. Align the lease utility exhibit before promising independent procurement.
A co-located supply proposal may trigger a separate approval routeSection 39.169 applies to specified existing generation/net-metering arrangements, with statutory exceptions.
Texas basis. The section addresses new large-load net-metering arrangements with generation registered as stand-alone on September 1, 2025, and provides for notice, system-impact study and PUCT action. Texas Utilities Code §39.169
Campus consequence. Leasing space beside an existing generator is not automatically a ready-to-use private utility structure. Conditions can affect supply, curtailment and the capacity available to serve tenants.
Resolve before commitment. Have counsel determine whether the proposed arrangement falls within the section or an exception. Obtain the current utility and ERCOT process position before executing supply-dependent tenant commitments.
01 / CAMPUS EXPOSURE
Follow the consequences.
Authority
Have utility counsel and the provider confirm the proposed retail, master-meter or other arrangement before it enters lease language. Cooperative customer-choice assumptions require particular care.
Metering
Define revenue and operational meters, losses, common loads and dispute handling. A tenant should know which measurements determine its payment and which costs remain shared.
Credit
Assign minimum charges, deposits, nonpayment and vacancy exposure. Check whether the owner must keep paying the provider when it cannot collect from one tenant.
Service continuity
Define outage notices, curtailment authority, operator access and restoration. Separate service rights where feasible so one tenant's dispute does not become everyone's operating problem.
Claims and transfer
Make environmental claims traceable to the actual procurement and allocation. Test what changes when a tenant assigns its lease or a building is sold to a different owner.
COMBINED FAILURE TEST
A billing dispute coincides with a building sale
Test a tenant withholding shared charges while a building changes owner and the provider still requires full payment from the existing customer. The service and credit model needs a funded transition and an agreed dispute path, not just a normal-operation allocation formula.
Questions to take to the project team
Does the actual provider support every procurement and billing right promised in the leases?
Who pays shared losses, reserve equipment and minimum commitments during a tenant dispute?
Can one building be sold without rewriting every other tenant's service arrangement?
02 / RESPONSE CHOICES
When to advance. When to stop.
These are decision conditions, not universal thresholds. Confirm the evidence with the responsible providers, specialists and affected tenants before the owner authorizes a commitment.
Separate direct service
Advance whenThe provider supports separate customer relationships and the additional connections, land and metering are deliverable.
Stop or revise whenThe leases promise direct service that the provider has not agreed to support.
Tradeoffs and scope
Where supported, use distinct provider relationships and meters. Compare clearer customer boundaries with additional connection cost, land and coordination requirements.
Use a validated shared model
Advance whenThe legal and provider basis, auditable billing, operating duties and landlord credit exposure are accepted.
Stop or revise whenA submeter is being treated as proof of resale authority, independent choice or insulation from another tenant's default.
Tradeoffs and scope
Establish a lawful arrangement with transparent allocation, operator duties and tenant consent. Price landlord credit and operating exposure rather than assuming the utility bill can simply be passed through.
Redesign the commercial offering
Advance whenRevised tenant promises align with the actual service arrangement and preserve a viable leasing proposition.
Stop or revise whenThe commercial team keeps the original unsupported rights in a side letter or marketing commitment.
Tradeoffs and scope
If requested tenant rights conflict with the territory or shared network, change the lease promise or infrastructure before execution. Do not leave compliance to a later operating agreement.
The work Sitebraid would take on
Sitebraid would align the physical network with the provider, customer, metering, credit and ownership structure. We would expose contradictions between lease expectations and utility terms, coordinate a supported model with counsel and the provider, and carry it into design and funding decisions. We do not act as substitute regulatory counsel or promise retail rights that the campus does not possess.
03 / DECISION GATE
Evidence before commitment
Written legal and provider basis for the proposed service and billing arrangement.
Tenant-approved meter, cost-allocation, continuity and dispute provisions.
Funded operator and credit obligations that survive vacancy, transfer and default.
NEXT ACTION
Start here
Put the utility agreement and proposed lease utility exhibit side by side. Every right the lease promises but the service arrangement does not support is a development problem to resolve before signing.
A free owner-side guide to financial security, CIAC, customer-built interconnection facilities, TSP takeover and audit-ready documentation under adopted 16 TAC 25.194, effective October 8, 2026.
A premium owner-side draw request, monitoring, cost-to-complete, schedule-control and future-funding template for customer-built or build-transfer switchyards.
A free owner-side guide to Batch Zero eligibility, attestations, TSP and DSP handoffs, study data, energization and audit-ready evidence under ERCOT PGRR145.
Reviewed September 10, 2026. The scenarios and decision tests are Sitebraid analysis. Source materials establish context, not approval of a particular project. Applicable law, provider terms and technical requirements require project-specific confirmation.
Cooperative customer choice and service arrangements have a distinct statutory framework. Counsel and the actual provider must establish which structure is lawful for the campus.